Solar on a council building is worth most when it's sized to what that building uses during the day. A leisure centre with a pool uses almost all of a well-sized system's output; a school, empty through the sunniest weeks, can export much of it. Your half-hourly data measures the share at each system size, replacing the guess most estimates start from. The analyser passes the measured figure to the solar calculator, which works out what fits, what it costs and how soon it pays back.
Why measure before you size
- Every unit used on site replaces a unit bought at the full import price.1 Export earns far less: under the Smart Export Guarantee, a supplier pays for exported power from systems up to 5 MW, at a rate the supplier sets.2
- Rooftops rarely need planning permission in England, though listed buildings, conservation areas and car park canopies need more care, and almost every system needs network operator approval under G99.3
- On-site renewable plant is exempt from business rates in England from April 2022, which matters because councils pay rates on many of their buildings.4
- There are ways to pay without capital. Power purchase agreements need none, and grant rounds have funded solar on schools and community buildings.5

The figure that matters most: the share you use yourself
At a 25p unit price, each kWh of solar used on site saves 25p, while each kWh exported earns about 5p, the rate the calculator assumes.1 That five-to-one gap means the share used on site moves the result more than almost any other input.
The calculator starts at 80% if you don't measure it.1 For a leisure centre that's usually too cautious. For a school or a library that closes at weekends, it can be too generous at almost any size. Half-hourly data settles it.
What your half-hourly data shows before you size anything
| What the data shows | Why it matters for solar |
|---|---|
| Summer daytime demand, weekdays and weekends | Sets how much output you can use. About three quarters of a year's solar output comes from April to September.6 |
| Base load | What's running on a sunny Sunday afternoon. In a leisure centre it's high, which is why so little is exported. |
| School holidays | The summer holiday is the sunniest stretch of the year, and the emptiest for a school. |
| Cooling on hot afternoons | Gym and office cooling line up with peak solar, so solar trims the year's highest import. |
| Peaks against agreed capacity | Background for the network operator's G99 assessment, and headroom for heat pumps later. |
How council buildings differ
In our worked leisure centre example, the centre would use every unit from a solar system of up to about 180 kWp, because pool plant runs around the clock. Depots and civic offices use most of their output on weekdays. Schools and libraries need smaller systems for the same roof, or a battery or export arrangement to make a bigger one pay. See solar on council buildings.
From your data to a solar estimate
- Load a year of half-hourly data for each main meter into the analyser. It runs in your browser. Need the files? See getting half-hourly data.
- Open the building's Solar tab. Add the postcode to set the sunshine for your area. The tab shows output, share used on site and share of the building's electricity at each size.
- Choose "Size solar for this site". The calculator opens with your figures. Draw the roofs and car parks on the map, and it sets the share used on site for the system that fits, then works out cost, savings and payback.
Only the annual use, the share used on site at a dozen sizes and the postcode, if entered, are passed, after the # in the web address. See the privacy notice.
What the solar calculator does
The solar calculator on this site uses the same method as the UK Solar Calculator, built by the same team.
- Measures roofs and car parks from satellite imagery or dimensions you enter, for pitched and flat roofs, ground mounts and carports.1
- Estimates generation at your postcode from the SAP 10.3 regional sunshine data.1,7
- Prices the system from UK benchmarks per kWp, including an inverter replacement in year 13.1
- Compares buying with a PPA over 25 years, and models a battery if you want one.1

What this can and cannot tell you
The analyser's estimate uses a typical UK solar day scaled to your region and the UK's seasonal pattern. It doesn't know about cloudy weeks, shading from plant or neighbouring buildings, roof orientation, or changes you'll make, such as adding heat pumps or EV charging. Treat it as a planning figure. The calculator's results are estimates, not a quotation.1,3
Questions people ask
Will a council building use all the solar it generates?
It depends on the building. A leisure centre with a pool often uses almost all of a well-sized system's output, because pool plant runs around the clock. Schools, libraries and offices that close at weekends or in holidays export more. Measure it from the building's own half-hourly data.
Is the 80% default in the solar calculator right?
It's a starting guess. For leisure centres it's usually too cautious; for schools it can be too generous. The analyser replaces it with the share measured from your data at each system size.
Should schools have smaller solar systems?
Often, yes, unless there's a battery, holiday use of the building or a good export arrangement. The summer holiday is the sunniest and emptiest stretch of a school's year.
Do I need a battery?
Not usually on a building that uses most of its output, such as a leisure centre. A battery can help where a lot is exported, for example a school in summer or a depot charging vehicles overnight. Check how much the building exports at your chosen size first.
Sources
- How the solar calculator works (method and assumptions)
- Ofgem: Smart Export Guarantee (SEG)
- Solar planning permission and grid connection
- Explanatory Memorandum to SI 2022/405, business rates exemption for renewable plant
- Paying for solar on council buildings
- Department for Energy Security and Net Zero: Energy Trends section 6, renewables (table ET 6.1, solar generation by quarter)
- GOV.UK: Standard Assessment Procedure (SAP 10.3)