Agreed supply capacity is the most your connection is contracted to take, in kVA, and it's on your electricity bill. Convert your busiest half hours from kW to kVA (divide by the power factor), keep a safety margin, and the gap is your headroom. For heat pumps, test the heating months only: summer chiller peaks don't matter for a load that runs from October to April.

Why capacity decides decarbonisation plans
Most routes to net zero on a council estate move heat from gas to electricity. A heat pump producing 300 kW of heat at a seasonal efficiency (COP) of 3 draws about 100 kW of electricity. Switching a refuse fleet, pool cars or minibuses to electric adds charging load at the depot, often overnight. If the connection can't take it, the network operator (DNO) has to increase it, which can take years and cost far more than the plant. See depots and fleet and heat networks, which can avoid the question for buildings in a zone.
kW, kVA and power factor
Half-hourly data gives average demand in each half hour, in kW. Capacity is set in kVA, which also counts reactive power drawn by motors, fans and older lighting. The link is the power factor:
Working out headroom from half-hourly data
- Use at least a full year, so you catch both winter heating peaks and summer chiller peaks.
- Enter the agreed capacity from the bill and your power factor (0.95 if you don't know it).
- Keep a margin, typically 10%, for growth and short spikes the half-hour average hides.
- Read the firm headroom: the largest constant extra load that fits in every half hour of the year.
- Test the real load. The analyser's headroom test takes a load in kW, the hours it runs and whether it runs all year or October to April only, and counts the half hours it would push over the limit.
In our worked example, a leisure centre on a 250 kVA supply has 58 kW of firm headroom across the year, because a July hot spell sets the peak. Tested over the heating months, a 60 kW heat pump fits and a 90 kW one doesn't.
What to watch on a council estate
- Leisure centres run close to their limits. Pools have high, steady demand, so a pool heat pump often needs careful sizing or a capacity increase. Test it over the heating months.
- Depots charge overnight. Overnight fleet charging usually fits in the trough, but a whole fleet arriving back at once does not. Test the real charging pattern, and look at smart charging to stagger it.
- Schools peak in winter mornings. Heating start-up, kitchens and IT all land at once. Test a heat pump against those mornings, not the average day.
- Several meters, one connection. Where a site has more than one meter behind one connection, add them up before comparing with capacity. The analyser can group meters into one site.
What half-hourly data can't tell you
Half-hour averages smooth out spikes such as motor starts, so treat the result as an early screen, not a design. Network capacity upstream of your site, fault levels and the cost of an increase come from the DNO. Use the analyser to decide which option to take to them, and to show them your measured profile.
Solar and your connection
Solar lowers daytime import but adds export capacity questions under G99. On a long-hours building such as a leisure centre, most output is used on site, so export limits rarely cost much; on a school closed for the summer, they can. See solar planning and grid connection.
Questions people ask
Where do I find our agreed supply capacity?
On the electricity bill, usually as agreed, authorised or available capacity in kVA. Your supplier or DNO can confirm it, and the connection agreement sets it.
Why test a heat pump over the heating months only?
Because it runs mainly from October to April. A summer chiller peak sets the all-year headroom figure, but it does not coincide with heat pump load.
What power factor should I use?
Use the figure from your bill or power quality data if you have it. If not, 0.95 is a reasonable starting point; it is probably lower if you pay reactive power charges.
Is this enough for a DNO application?
No. It is the evidence to decide what to ask for. The DNO studies the network and makes the formal offer.